Spain
Comprehensive dismantling of the priming line at the BSH plant in Zaragoza.
The project had very demanding deadlines set by BSH. Movilex had 9 days to fully carry out the dismantling, a job that was ultimately completed in 6 days, thanks to the team’s planning, experience, and professionalism.
This early completion of the deadlines represented a distinctive result compared to other dismantling companies involved in the project, none of which met the established targets.
Main functions and responsibilities of Movilex
During the dismantling, ferrous materials, aluminium-copper, stainless steel, electric motors, electrical panels, boilers, and other industrial equipment were recovered.
Most of the recovered material was sold to local companies, supporting the local circular economy.
Movilex also managed hazardous waste, including gas decontamination from air-conditioning equipment, noise-reduction blankets, and the ceramic dust present in the priming booths, ensuring it was treated in accordance with current regulations.